$40 million, 250,000 sq. ft., new 460v electrical service; new telecommunications systems.
Managed infrastructure upgrade of AT&T’s corporate headquarters (NYC). This was a fast-track design-build undertaking whereby AT&T consolidated operations, economized real estate usage, and sold its flagship building in NYC to a high technology-oriented owner, and remained as the anchor tenant.
 |
Provision of value engineering services – recommend design and engineering options that meet budget constraints, and schedule. Provide material substitutions. |
 |
Served as the liaison between AT&T’s program manager, real estate asset manager, operations personnel, architects, engineers, code consultant, and telecomm. consultant. |
 |
Internal consulting to AT&T’s real estate team including broker (Eastdil) and prospective buyer (Rudin Management). |
 |
Ensured that construction and engineering activities were congruent with the operational needs of the building. |
 |
Ensured that Barney Skanska’s engineers coordinated activities to dovetail with building operations including facilitating maintenance. |
 |
Reconciled project costs; maintained and updated budgets; provided general conditions and cash flow projections, and tracked general conditions efficiencies relative to construction progress. This was done across an increasing number of sub-projects |
 |
C. of O. conversion of building to expedite sale of building. |
 |
Additional work on non-AT&T floors to allow for early occupancy of new tenants. |
 |
Infrastructure upgrades (demolition, abatement, and electrical) requested by new owner. |
 |
Managed bidding process. Conform to AT&T’s quality management program (ISO 9001). Pre-qualified vendors and contractors. Reviewed scopes of work for accuracy and completeness Reviewed bids for technical content, contract compliance, scope compliance, specification compliance, and schedule adherence. Negotiated pricing with contractors. |
 |
Completion of $500,000 fire alarm system upgrade project in six months. This was a project that was ongoing for four years and which was mis-managed by previous parties to the extent that AT&T had to hire Barney Skanska as the CM to solve a host of problems. I managed to resolve the technical and engineering problems, lack of administrative management and controls, and absence of estimating and purchasing documents. I researched existing documents, recreated the contract, and established new, accelerated milestone dates for completion, testing, and inspections. |
 |
Successfully completed the replacement of the building’s cooling plants including chillers and cooling towers (during the winter of 1998). |
 |
Renovated corporate kitchen and cafeteria (1998) - $1.5 m, 15,000 sq. ft. in 12 weeks. This included new food service equipment and significant electrical upgrades. We saved AT&T $100,000 by making several bidding strategy decisions that contradicted AT&T’s findings. Our steadfastness proved to be essential, and was appreciated by AT&T after favorable results were delivered. |
OFFICE CONSTRUCTION
 |
| Project : METLIFE |
|
$12 million, 175,000 sq. ft., offices and data centers. |
| |
|
|
| Project : UNICEF (1996) |
|
$6.2 million, 97,000 sq. ft., six floors with a 24 hour data center. |
| |
|
|
| Projec t : FOLEY SQUARE COURTHOUSE (1992 – 1995) |
|
$130 million, 750,000 sq. ft., forty two state-of-the art courtrooms, 41 judges chambers, public assembly areas, 15,000 sq. ft. ceremonial courtroom, kitchen/cafeteria, and detention center. |
| |
|
|
| Project : ITT SHERATON / SHERATON NEW YORK |
|
INFRASTRUCTURE UPGRADE (1990 – 1991) $95 million
|
| |
|
|
TECHNOLOGY / PROJECTS

 |
Toronto Transit Commission / Systems Implementation for Subway Monitoring and Control / $17M / Toronto, ON |
 |
SEPTA / Civil, Electrical and Signaling Construction for Subway Infrastructure Upgrade / $70M / Philadelphia, PA |
 |
MARTA / Systems Upgrade / $2M / Atlanta, GA |
 |
KCRC / Subway Extension / $5M / Hong Kong |
 |
Amtrak / Chicago Union Station / $2.5M / Chicago, IL |
|
|